| geo.nova@hotmail.com 2007-06-24, 1:25 pm |
| I'm told that here in NH I can expect to pay approx $85-$100 per hour
for general excavation work which should include all machine
transportation and operational costs (one backhoe). Does this sound
right to anyone? I want to agree on a fair price with an excavator. I
figure two days work from past experience with a similar job. I'm sick
of getting high lump sum quotes and want to offer payment by hour this
time.
Thanks in advance,
K.
| |
|
| yes of course demographics is everything
but even here in FL, that's a fair price
suppose the operator only wants to work about 4 hours
(which is a lot of operating time sorta)
that's still under 400 dollars.
is that a cool deal for all that excavating?
<geo.nova@hotmail.com> wrote in message
news:1182707391.140536.38230@p77g2000hsh.googlegroups.com...
> I'm told that here in NH I can expect to pay approx $85-$100 per hour
> for general excavation work which should include all machine
> transportation and operational costs (one backhoe). Does this sound
> right to anyone? I want to agree on a fair price with an excavator. I
> figure two days work from past experience with a similar job. I'm sick
> of getting high lump sum quotes and want to offer payment by hour this
> time.
> Thanks in advance,
> K.
>
Posted Via mcse.ms Premium Usenet Newsgroup Services
----------------------------------------------------------
** SPEED ** RETENTION ** COMPLETION ** ANONYMITY **
----------------------------------------------------------
http://www.mcse.ms
| |
| bambam@nospam.tnx 2007-06-25, 3:25 am |
| On Sun, 24 Jun 2007 10:49:51 -0700, geo.nova@hotmail.com wrote:
>I'm told that here in NH I can expect to pay approx $85-$100 per hour
>for general excavation work which should include all machine
>transportation and operational costs (one backhoe). Does this sound
>right to anyone? I want to agree on a fair price with an excavator. I
>figure two days work from past experience with a similar job. I'm sick
>of getting high lump sum quotes and want to offer payment by hour this
>time.
>Thanks in advance,
>K.
$100 -- 125 an hour is reasonable for a backhoe, depending on size.
If you are paying by the hour, don't forget the cost of trucks and
dump fees to haul the excavated earth away. And check on the
charge for delivering and removing the hoe.
Personally, I prefer a lump sum bid ... but I'm a contractor and
risk averse.
Ken
| |
| PeterD 2007-06-25, 9:25 am |
| On Sun, 24 Jun 2007 10:49:51 -0700, geo.nova@hotmail.com wrote:
>I'm told that here in NH I can expect to pay approx $85-$100 per hour
>for general excavation work which should include all machine
>transportation and operational costs (one backhoe). Does this sound
>right to anyone? I want to agree on a fair price with an excavator. I
>figure two days work from past experience with a similar job. I'm sick
>of getting high lump sum quotes and want to offer payment by hour this
>time.
>Thanks in advance,
>K.
Perhaps OK. Depends on the soil, which varies substantially here in
NH. I've sand where I am, and I can do stuff in an hour that were
there a lot of rocks or ledge might take days....
Hourly costs of $85 to $100 seem (to me) reasonable.
However, I usually just rent the equipment and do the labor myself.
That way I find I can do the work and cleanup at an easier pace.
|
|
|
|
|